73 Results Found
Modern quality management and project management are complementary. They both emphasize customer satisfaction and the underlying belief that quality leads to customer satisfaction. The main objective in quality management is making sure that the project meets the needs it was originally created to meet—nothing more, nothing less. In other words, to ensure quality, you must meet the needs of the stakeholder.
The question of how a project manager working in a functional or matrix organizational structure gets team members to perform is asked in almost every project management class I have taught.
Are you prepping for the PMP exam? What should you know about the impending new edition of A Guide to the Project Management Body of Knowledge PMBOK® Guide before scheduling your examination?
Projects are a social endeavor. Traditional project management approaches have shied away from the social advantages a more agile project environment brings. By nature, we are storytelling, pattern seeking and social people. We need colocation to shine truly in a project environment.
You are estimating the total project cost using three points for cost estimates with a 95 percent confidence level. What is the cost estimate range if the estimated project cost is $120,000 and the standard deviation is $2,500?
You are the project manager on a construction project where you are deliberating between renting, leasing or purchasing a large piece of equipment. Equipment pricing: Rent at a cost of $2,500 per day; Lease for a 60 day period at $2,500 per day, with a 10% discount; Purchase at a price of $100,000. By looking at your project schedule, you have estimated that you will use the equipment about 50 to 60 days. Based only on price, which decision would you recommend?
Your organization and a seller have just agreed to a contract with a total cost of $150,000, an estimated profit of $10,000, buyer/seller sharing of 70/30 and a ceiling price of $170,000. What is the PTA (point of total assumption)? A. $170,000 B. $160,000 C. $164,2...
In this blog series, we'll get you up to speed on using the key tools listed in the PMBOK® Guide, including Decision Tree Diagrams.
Accessing cloud-based resources, whether they be IaaS/PaaS/SaaS-based, is very convenient. With a browser and Internet connection, you are up and running. No driving to your work office, no need to log into the corporate network. Just open up your web browser and go. This convenience, however, comes with a security risk. All of your business work is conducted over an insecure communication network. Unlike your office network, where the network link between you and the data center is under corporate control and is physically secure, the cloud access link is over the Internet.
In this blog series, we'll get you up to speed on using the key tools listed in the PMBOK® Guide. First up, Work Breakdown Structure (WBS).