PMP Question of the Week: Develop Project Charter

By Guest Authors
June 22, 2015

pmpweek04When is a contract an input to the Develop Project Charter process?

A. When all or part of the project is being done for an external customer or by a contractor.
B. When the project is being done for an internal customer.
C. Always.
D. When the project manager decides to include it in the project charter.

Reveal Answer

The correct answer is A.

A contract is used when work is being done for an external customer or when a contractor is doing the work for the project team.

Related Resources
PMP Exam Prep Mobile App
Project Management White Papers

Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program

In this article
  • Certification
  • PMP
  • Project Management
  • pmp
  • pmp exam
  • pmp exam prep
  • project management

Join the Conversation Cancel Reply

Will not be published.


RELATED ARTICLES

  • Quick Look at the PMBOK® Guide: Sender and Receiver Model

    In this blog series, we'll get you up to speed on using the key tools listed in the PMBOK® Guide, including Sender and Receiver Model.
    By Richard Perrin June 5, 2015
  • PMP Exam Prep Question of the Week

    You are using earned value status formulas to assess your project’s performance. The first term you use in each formula is _________________.
    By Guest Authors October 7, 2013
  • PMP Formula of the Week: Schedule Performance Index of 1

    What condition does a Schedule Performance Index (SPI) of 1 mean for a project?
    By Guest Authors September 7, 2015

CONNECT WITH US

CATEGORIES

Back to top

© 2018 Global Knowledge Training LLC. All Rights Reserved.  Site Admin | Logout