• About Us
  • All Categories
  • Contact
  • Home
  • Our Authors
  • Partner Quizzes (Testing) > Sirius Computer Solutions
  • Global Knowledge Blog Global Knowledge Blog

--

  • Home
  • All Categories
  • Our Authors
  • About Us
  • Global Knowledge Blog
  • Home
  • All Categories
  • Our Authors
  • About Us

PMP Question of the Week: Task Duration Predecessor

By Guest Authors
December 22, 2014

pmpweek07Your project has the following tasks:

Task Duration Predecessor

Name Duration (in weeks)
Predecessor
A 2
B 3 A
C 5 B
D 5 C
E 8 B
F 1 D, E

 

Management has promised the customer that you would complete the project in 14 weeks. What does this mean?

A. You have negative float.
B. You have positive float.
C. You have zero float.
D. You cannot calculate the float.

Reveal Answer

The correct answer is A.

The project has negative float because it currently does not meet the externally imposed date. The critical path is 16 weeks, while the customer was told 14 weeks.

Related Resources
PMP Exam Prep Mobile App

Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program

In this article
  • Certification
  • PMP
  • Project Management
  • pmp
  • pmp exam
  • pmp exam prep

Join the Conversation Cancel Reply

Will not be published.


RELATED ARTICLES

  • PMP Exam Prep Question of the Week

    A project sponsor has requested information about the cost performance on a project, so you need to determine cost variance. What formula should you use?
    By Guest Authors September 30, 2013
  • PMP Question of the Week: Change Request

    In response to evidence that the primary supplier will not meet the delivery requirements, a change is requested to begin procuring the required items from a backup supplier according to...
    By Guest Authors August 11, 2014
  • PMP Question of the Week: Statement of Work

    You are putting together a statement of work (SOW) to be included in a signed agreement with a seller. Which of the following statements about this SOW is false?
    By Guest Authors February 23, 2015

CONNECT WITH US

CATEGORIES

Back to top

© 2019 Global Knowledge Training LLC. All Rights Reserved.  Site Admin | Logout