PMPFormulaOTW475166460Your organization and a seller have just agreed to a contract with a total cost of $150,000, an estimated profit of $10,000, buyer/seller sharing of 70/30 and a ceiling price of $170,000. What is the PTA (point of total assumption)?

A. $170,000
B. $160,000
C. $164,286
D. $166,453

[showhide type="post" more_text="Reveal Answer" less_text="Hide Answer"]

The correct answer is C.

The formula to calculate PTA is: ((Ceiling Price - Total Price)/buyer's Share Ratio) + Total Cost

Find the total price: 150,000 (Total Cost) + 10,000 (Profit) = 160,000. Then, use the formula above to calculate PTA:
=((170,000 - 160,000) / .70) + 150,000
=(10,000/.7) + 150,000
=14,286 + 150,000
PTA = $164,286

[/showhide]

Related Resources
PMP Exam Prep Mobile App
Project Management White Papers

Related Courses
IT Project Management
Project Management Fundamentals
Project Management, Leadership, and Communication
PMP Exam Prep Boot Camp

 

Cookie Control toggle icon